COFA Construction

18.07.2011
Client: UNSW
Architect: Architectus

Site retention works are underway for the Universities new facilities at their Paddington campus.  Strengthening works have been progressing all year in the refurbished sections in a piecemeal fashion as the COFA site remains operational during construction and detailed decanting of the laboratory and workshops is required.  A mini piling rig was required due to the close proximity of the heritage building to reduce the risk of disturbing the high level sandstone foundations.  The new facilities will soon start to take shape and a state of the art laboratory, workshop and gallery space will transform the current campus into a world class teaching and research centre.